|
To view information around the capital funding campaign, please visit the Capital Campaign Page.
Updated project status photos are available at http://picasaweb.google.com/bobvolkman/CornerstoneChurchYouthBuildingProgressPhotos
Week of October 4th
- Carpet
- Landscaping
- Site grading and seeding
- HVAC installation
- Painting
- Doors and hardware
- White boards, towel & soap dispensers, shower curtains
Week of September 27th
- Painting
- Cabinets
- Site grading
- Plumbing fixtures
- Toilet partitions
- Lighting
Week of September 20th
- Completed cloud in lounge area
- Completed cloud in worship area except for ceiling tile
- Painting
- Ceiling grid complete
- Completed Floor tile in restrooms, entrances and lounge area
- Air Conditioning & Heating
- Electrical fixtures, outlets, etc
- Rolling door for A/V room
- Site grading and topsoil spread
- Bench on patio
Week of September 13th
- Drywall finishing
- Heating and air conditioning equipment and ductwork
- Network and telephone cabling installed
- Soffits and gutters complete
- Finish carpentry for patio area
- Paving and striping of all parking lots complete
- Site Grading in rear
Week of September 6th
- Insulation complete
- Electrical rough-in complete
- Drywall almost complete
- Heating and air conditioning equipment and ductwork
- Grading for front parking lot
- Site Grading in rear
- Meter Pit on Weathersfield for fire hydrant water
Week of August 30th
- Insulation almost complete
- Electrical rough-in complete
- Drywall
- Heating and air conditioning equipment and ductwork
- Siding complete
- Concrete work complete
- Restroom Plumbing
- Duke Energy Transformer replaced
- Grading for front parking lot
- Site Grading in rear
- Water Line installed for new fire hydrant
- Inventory for furniture, etc. complete
Week of August 23rd
- Insulation almost complete
- Electrical rough-in complete
- Drywall
- Heating and air conditioning equipment and ductwork
- Siding complete
- Concrete work complete
- Restroom Plumbing
- Duke Energy Transformer replaced
- Grading for front parking lot
- Site Grading in rear
- Water Line installed for new fire hydrant
- Inventory for furniture, etc. complete
Week of August 23rd
- Audio/Visual conduit and wiring installed
- Insulation
- Drywall started
- Heating/Air Conditioning equipment installed
- Siding on South and East walls complete
- Site grading
Week of August 16th
- Most interior framing complete
- Most electrical and HVAC rough-in complete
- Shower units installed
- Exterior Doors and windows complete
- Insulation in ceiling
- Exterior siding started
- Concrete sidewalks and pads
- Site Grading continues, Pond outlet complete
- Subgrade for new parking on NE corner (ready for parking)
- Prework for transformer replacement
Week of August 9th
- All exterior Framing, sheathing complete
- All exterior wall masonry complete
- Most windows are installed
- Most interior walls are framed
- Started framing for platform and cloud
- Continued HVAC and Electrical rough-in
- Continued grading in rear, new parking spaces ready for subgrade
Week of August 2nd
- Continued Framing, trusses, sheathing
- Completed Roof
- Completed masonry on North wall
- Completed plumbing rough-in
- Started window installation
- Started HVAC and Electrical rough in
- Continued retention pond sitework
Weeks of July 19th and July 26th
- Continued building framing, trusses, sheathing
- Continued retention pond including installed outlet
Week of July 12th
- Framing for exterior walls and most of the classrooms
- Block firewall between new and existing buildings
- Plumbing for the new roof drains
- Connections for the existing roof and parking lot drains to the pond
- Partial completion of the outlet for the detention pond
- Conduit and bases installed for new parking lot lights
Week of July 5th
- Completed wall foundations
- Installed underground electrical and conduit for A/A system
- Poured concrete floor
- Completed installation of conduit for new electrical service
- Continued work on storm drainage systems and detention ponds
Weeks of June 22nd and June 29th
Monday - Friday
- Completed sanitary sewer installation
- Installed underground plumbing for restrooms and mechanical rooms
- Instlled 3/4 of wall foundations
- Started installation of electrical service for new building
Week of June 15th
Monday - Friday
- Started foundations for new building
- Started storm sewer extension on west and south of building
Week of June 8th
Monday - Friday
- Rain most of the week. Only worked 1.5 days
- Filled area of new building pad
Week of June 1st
Monday - Friday
- On and off rain all week
- Continued shaping the retention pond when possible
- Building permit approved 6/5/2009 allowing work to start on new building
Week of May 24th
Monday - Friday
- On and off rain all week
- Continued shaping the retention pond when possible
Week of May 17th
Monday - Friday
- Good weather all week
- Continued shaping for detention ponds
- Surveyed for north parking extension and sewer systems
- Materials required for sewers were delivered
- Stripped topsoil for north parking extension
Prayers needed: Continued good weather and final building permit approval.
Week of May 10th
Monday - Wednesday
- Continued shaping detention ponds
Wednesday - Thursday
Friday
- Continued shaping detention ponds
Week of May 3rd
Monday
- Started earthwork for new stormwater detenton ponds (Earthwork includes reshaping the hills between the church and Weathersfield to form a new, larger detention basin for stormwater runoff)
- Sawcut parking lot for removal for new sewer lines
- Marked out undergound utilities for new electrical service
Tuesday
- Continued earthwork: most topsoil has been scraped off, started shaping detention pond.
Wednesday
Thursday and Friday
- Little work with soil saturation from Wednesday's rain. All of the existing roof drains and the parking lot drain to the old detention ponds, so the area of earthwork in the back gets a lot of water, with some areas flooded.
Prayer: Continue to pray for dry weather.

Week of April 26th
Completed survey layout to start earthwork. Installed silt fences required to control erosion runoff when doing earthwork. The earthwork includes reshaping the hills between the chuch and Weathersfield to form a new, larger detention basin for storm water runoff. After earthwork, they will be installing underground utilities for water and sewers and excavating for the building foundations.
Prayer: Pray for dry weather!!!
Groundbreaking - April 26th
We have broken ground and we are ready to move forward with the site preparation and construction. Together with building construction, you will see some things happening with the new sign on 747 and lighting along the entrance/exit. Please cover in prayer a West Chester zoning meeting on May 13th, during which we will be asking for a variance due to the size of the sign. West Chester has severe restrictions on sizes and we know we need a permanent sign that is bigger than 3' x 5'!
Thank you for you support in both prayer and financial giving that make this project possible.
|